RIBA Plan of Work 2020
The RIBA Plan of Work is published by the Royal Institute of British Architects (RIBA). Split into a number of key project stages, the RIBA Plan of Work provides a shared framework for design and construction that offers both a process map and a management tool.
The RIBA Plan of Work 2020 replaced the 2013 edition. It changed the structure of the stages as shown below:
Stage | 2013 | 2020 |
0 | Strategic definition. | Strategic definition. |
1 | Preparation and brief. | Preparation and briefing. |
2 | Concept design. | Concept design. |
3 | Developed design. | Spatial coordination. |
4 | Technical design. | Technical design. |
5 | Construction. | Manufacturing and construction. |
6 | Handover and close out. | Handover. |
7 | In use. | Use. |
Changes have been introduced in relation to the digitisation of the industry, modern methods of construction, increasing awareness of ethics, the importance of sustainability, the value of aftercare and different approaches to the timing of planning applications and procurement.
The green overlay and BIM overlay which were separate additions to the 2013 edition have now been incorporated into the plan itself. Nine project strategies have been introduced to tease out specific briefing issues and to allow the lead designer to coordinate design team contributions into the broader design.
Professor Alan Jones, RIBA President wrote: ‘The biggest addition to the new RIBA Plan of Work comes in the form of the new sustainably project strategy. This challenges design teams to design with a focus on sustainable outcomes from the outset of the project… In addition to the sustainability changes, this update has concentrated on improving the guidance in relation to the planning process, procurement and information requirements at each stage. Most importantly we have set out detailed stage descriptions and new guidance on core project strategies.’
The RIBA Plan of Work 2020 is available at: https://www.architecture.com/knowledge-and-resources/resources-landing-page/riba-plan-of-work
[edit] Related articles on Designing Buildings Wiki
- BREEAM and RIBA stages.
- BSRIA guidance on project information process BG 78/2021.
- Comparison of BIM work stages.
- Enterprise asset management.
- Governance for Railway Investment Projects (GRIP).
- NBS.
- OGC gateway review.
- Plan of work.
- Project lifecycle for major road projects.
- Record keeping.
- RIBA Plan of Work for Fire Safety.
- RIBA plan of work v project plans v OGC gateways.
- RIBA plan of work.
- RIBA.
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.